Month of August 2019

Cumby Sign

 

  • Asbestos Abatement work to be completed by Friday, August 9, 2019. Connell-Greene Consulting, Inc. to issue the Clean Air Certificate.
  • The specified soil erosion controls and existing tree protection to be installed by W.S. Cumby’s site subcontractor starting Wed., August 7, 2019. Upon completion of these two items, Lower Merion Township’s arborist and building inspector will inspect the completed work for township compliance; upon receipt of their approval, W.S. Cumby is expecting the release of the approved Lower Merion Township Building Permit.
  • The removal of approximately. 3-5 existing trees in, or close to the construction area footprint has been scheduled for the week of August 12, 2019.
  • W.S. Cumby’s mechanical, electrical, and plumbing subcontractors will be working in the existing Parish House the week of August 12 to disconnect and cap existing utilities, in preparation for the start of the bulk demolition work.
  • W.S. Cumby’s bulk demolition subcontractor, Diplomat Demolition Company, is intending to commence all operations during the week of August 19, 2019 for the complete demolition and off-site removal of the front portion of the existing Parish House. This bulk demolition work is anticipated to take four weeks to complete. Interior demolition work, excavation, and foundation work will start immediately thereafter.